Texas Department of Transportation Updates Road Work in Greenville Area

The Texas Department of Transportation has provided the latest updates on ongoing road work in Greenville and surrounding areas. Here are the details:

UNT County: SH 11, from Culver Street to Live Oak:

  • Work zone signs and barricades have been placed.
  • Signal work has been in progress at various locations.
  • Sod placement at various locations is completed.
  • Drivers are advised to be cautious of workers and watch for work zones in the area.

FM 1563, from SH 50 to SH 2655:

  • A 2.7-mile rehabilitation project to widen the existing roadway.
  • Work zone signs and barricades are set up.
  • Right of way preparation, driveway installations, and cross culvert work are ongoing.
  • Culvert extension and subgrade widening work are in progress.
  • Drivers are urged to be vigilant of workers and work zones.

FM 2642, from FM 35 to SH 66:

  • Work zone signs and barricades are in place.
  • Excavation work for detour is ongoing.
  • Saw cutting of existing roadway for detour tie-ins is being performed.
  • Traffic has been shifted west for asphalt, concrete removal, and driveway removals.
  • Storm sewer placement has commenced.
  • Motorists are reminded to watch for work zones and workers.

FM 2649, from I-30 to FM 1567:

  • Barricades and work zone traffic signs are set up.
  • Cross culvert work is complete, subgrade widening and cement treatment near mile six are finished.
  • Riprap and erosion control work is ongoing.
  • Drivers are advised to be cautious of workers and work zones.

Shelby Avenue and Bledsoe Creek Bridge:

  • Barricades and work zone signs are placed.
  • Concrete deck pouring on Shelby Ave is completed.
  • Bledsoe Creek project in Fannin County has started on backwalls and right-of-way prep.
  • Motorists are reminded to be aware of workers and work zones.

I-30 Intersection Improvements from Monte Stratton to FM 1903:

  • Barricades and advance warning signs are set up.
  • Eastbound mainlane barrier shift work is planned, along with low-profile traffic barrier placement at FM 1903.
  • Excavation and embankment work for detour placement is ongoing.
  • Utility work is in progress, and temporary ramps are open.
  • Main lane widening and drainage work are upcoming.
  • Drivers are urged to be cautious of workers and work zones.

Hunt and Rains Counties Maintenance Crews:

  • Various sign and mailbox installations on various roads.
  • Potholing work is scheduled.
  • Winter weather preparations are in progress.

Motorists are encouraged to stay informed about these updates, exercise caution, and watch for work zones when traveling in these areas.