On Tuesday, March 28, the Greenville City Council unanimously passed a resolution authorizing the publication of a Notice of Intention to issue Certificates of Obligation in a principal amount not to exceed $65,000,000. The $65,000,000 Recreation Center Project is planned to include the construction of a new recreation/athletic/aquatic center to be located at the Greenville SportsPark and expansion to the Reecy Davis Recreation Center.
The Project Goals are revenue neutral with no increase in City Taxes (senior’s taxes are frozen) and focus on regional attraction and addressing overcrowding.
Project Timeline:
|
Program Verification |
March – April 2023 |
|
Schematic Design |
May – August 2023 |
|
Design Development |
September – November 2023 |
|
Construction Documents |
December 2023 – March 2024 |
|
Bidding / Permitting |
April – May 2024 |
|
Construction |
June 2024 – September 2025 |
Recreation Center Projected Cost Center
|
Overall |
$65,000,000 |
|
|
Construction Soft Cost |
$54,000,000 |
|
|
Greenville SportsPark |
$11,000,000 |
|
|
Greenville SportsPark Additions |
$8,700,000 |
|
|
Reecy Davis Recreation Center Expansion |
$7,000,000 |
|
|
Soft Cost |
$11,000,000 |
|